Can your estimator submit a bid from the job trailer if the main internet connection drops? Before you pay for a second connection, have the estimator upload a sample package from the desk where bids actually go out. Time the whole job, from switching connections to seeing confirmation. That number helps you decide whether to buy the service, change the setup, or put an authorized bidder at another location.
Say an Atlanta contractor has a bid due at 2 p.m. The price sheet is small, but the required attachments include marked-up drawings. Email still works on the trailer hotspot. What the operations manager needs to know is whether the estimator can sign in, upload every attachment, review the package, and confirm receipt before the portal closes.
Set up a bid rehearsal without submitting a live bid
- Build a representative package. Use dummy files with the same approximate sizes, file types, and number of attachments as a recent bid. Keep confidential estimates and client drawings out of the exercise.
- Use the actual desk and device. Have IT arrange a test window and confirm the estimator’s laptop is using the backup connection. Run the rehearsal during a typical working period with the usual crew activity.
- Test what the portal permits. Use a practice area if the owner provides one. Otherwise, time the transfer to an approved test destination and check portal sign-in separately. Record which steps you could verify. A transfer to another site leaves the portal’s own processing time unknown.
- Time each step. Record the minutes spent switching connections, signing in, transferring the files, and checking the result. In a practice portal, have the estimator find the receipt or confirmation screen a second person would use to verify submission.
Work backward from the deadline
Suppose a rehearsal takes 18 minutes from switching to confirmation. Your bid lead wants another 12 minutes for review or a retry. For a 2 p.m. deadline, that makes 1:30 p.m. the latest planned start on that tested route. Those numbers illustrate the calculation. Use your own results and allow more time when the final package is larger or the portal step remains untested.
The office fallback needs its own cutoff. If the office estimator needs 15 minutes to collect the approved files and 10 minutes to submit them, waiting until 1:45 leaves too little time. Name the person who can switch the work to the office, agree on a decision time, and make sure the authorized office bidder can retrieve the final revision under their own account.
What if the upload stalls halfway?
Assign one person to control the submission. If the trailer loses its connection after the estimator clicks Submit, have that person check the portal status or follow the bid owner’s published support instructions before anyone retries. Write down where the confirmation is saved. That lets the office distinguish an unfinished upload from a bid the owner already received.
What should your IT provider quote?
Ask for the cost of the backup service, the equipment in the trailer, installation, and a rehearsal with the estimating team. Check who monitors the connection, whether the data plan fits the size and frequency of your uploads, and who repeats the test when the trailer moves. Compare the recurring price with the practical alternative of submitting through a staffed office.
For other field and office responsibilities, see the Atlanta contractor’s guide to construction IT support. Bring a sample package size and your next bid deadline to trueITpros to discuss what your team needs tested.